Construction Update
January 2012 Status
Concrete - Structural concrete slab in Sanctuary has been poured and all interior structural footings and grade beams have been poured
Structural Steel - Structural steel columns and beams are being installed and will be complete by the end of the month
Wood Framing - Framing contractor is working on the interior and exterior walls and new structural supports
Plumbing- Underground plumbing has been installed
Windows - Shop drawings are being reviewed by the architect. Once they are approved we release the order